Seven dimensions, each with its own evidence

Where it stands, by unit and by dimension.

An enhanced geothermal development by Fervo Energy (listed on Nasdaq as FRVO since May 2026). Phase I is about 100 MW in three 33 MW GeoBlocks; a second phase of about 400 MW is under construction. Each dimension shows its latest sourced state for the scope you choose. A unit never inherits another unit’s progress, and nothing here adds up to a score.

Commissioning · Cape Station GeoBlock 2

Exporting test energy

GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

Test energy is not contracted commercial delivery.

Company reported Fervo Energy (SEC filing, Form 8-K exhibit) · Disclosed 9 November 2026

“GeoBlock 2 has achieved grid sync and is in its early operations phase, delivering test energy to the grid.”

Inspect primary source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗

Open question

Which tests has this unit passed on the way to service: cold and hot tests, grid synchronisation, test export?

Statements on record here (3)
  1. Target: first power, 2027: GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit) Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) · 12 August 2026 · Source ↗
  2. Synchronised to the grid: GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit) Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) · 9 November 2026 · Source ↗
  3. Exporting test energy: GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit) Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) · 9 November 2026 · Source ↗

Open this dimension in the ledger →Watch commissioning, GeoBlock 2

“Not established in reviewed sources” means the sources we reviewed do not say. It is not zero, a failure or a negative finding.

Quantities in context

Combined SCE and Clean Power Alliance contracted capacity including expansions
384 MWAs reported
Contracted under the Google PPA (GeoCluster expansion, expected online 2028)
396 MWAs reported
Contracted under the Shell Energy PPA
31 MWAs reported
Contracted under two Southern California Edison PPAs
320 MWAs reported
GeoBlock 1 net power production at commercial operation (company-reported)
33 MWAs reported · net
Initial phase as described in June 2024 (later restated as about 100 MW)
70 MWTarget: planned rating, not measured output
Next phase (Phase II), under construction
400 MWTarget: planned rating, not measured output
Phase I, approximately (three 33 MW GeoBlocks)
100 MWTarget: planned rating, not measured output

MW is power and MWh is energy; thermal (MWth) is not electrical (MWe). A planned rating says nothing about electricity generated. No capacity factor, readiness percentage or return is calculated here.

Stated targets

  • Target: commercial operation, 2026, per Utility Dive, stated 28 June 2024. Source ↗
  • Target: mechanically complete, Date not disclosed (GeoBlock 3), per Fervo Energy (SEC filing, Form 8-K exhibit), stated 12 August 2026. Source ↗
  • Target: first power, Q4 2026, per Fervo Energy (SEC filing, Form 8-K exhibit), stated 12 August 2026. Source ↗
  • Target: first power, Q4 2026 (GeoBlock 1), per Fervo Energy (SEC filing, Form 8-K exhibit), stated 12 August 2026. Source ↗
  • Target: exporting test energy, Q4 2026 (GeoBlock 1), per Fervo Energy (SEC filing, Form 8-K exhibit), stated 12 August 2026. Source ↗
  • Target: first power, 2027 (GeoBlock 2), per Fervo Energy (SEC filing, Form 8-K exhibit), stated 12 August 2026. Source ↗
  • Target: first power, 2027 (GeoBlock 3), per Fervo Energy (SEC filing, Form 8-K exhibit), stated 12 August 2026. Source ↗
  • Target: commercial operation, Jan 1, 2027, per Fervo Energy (SEC filing, Form 8-K exhibit), stated 1 October 2026. Source ↗
  • Target: commercial operation, Jan 1, 2027 (GeoBlock 2), per Fervo Energy (SEC filing, Form 8-K exhibit), stated 9 November 2026. Source ↗
  • Target: commercial operation, Jan 1, 2027 (GeoBlock 3), per Fervo Energy (SEC filing, Form 8-K exhibit), stated 9 November 2026. Source ↗

A target is what a party said it aims for, kept with the date it said it. It never sets a state. When a target moves, both versions stay on record.

Scoped alerts

Hear when this record changes.

Follow the whole project, one unit, or one dimension of one unit. You confirm the choice after signing in; nothing is followed until you do. Each briefing gives the previous state, the new state and the source.

To watch a single dimension, choose it above and use its watch link. Monitoring is part of Pro, $49/month. Reading every record stays free.

Explore the sampleGet the weekly briefing

Project history

Every statement on record, oldest first.

Quoted exactly and dated only as precisely as the source. Copies of one release count as one origin. A withdrawn statement stays visible and is labelled.

  1. 26 September 2023 · Permissions · Whole project

    Permission issued

    First environmental assessment with a finding of no significant impact, covering exploration activities only

    Secondary report Energy Global · Authority: Bureau of Land Management (Utah) · Jurisdiction: United States: federal (BLM), Utah

    “In February, the Utah Bureau of Land Management (BLM) approved the project’s first environmental assessment (EA), issuing a finding of no significant impact pursuant to the National Environmental Policy Act. This EA allows Fervo to commence exploration activities at Cape Station site.”

    Source: Energy Global ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  2. 26 September 2023 · Construction · Whole project

    Site work

    Groundbreaking for the exploration drilling campaign

    Secondary report Energy Global

    “Fervo Energy, a leader in next-generation geothermal technology, has held a groundbreaking ceremony to mark the start of its exploration drilling campaign at Cape Station”

    Source: Energy Global ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  3. 28 June 2024 · Customer / offtake · Whole project

    Agreement signed

    Two 15-year PPAs totalling 320 MW from Cape Station

    Secondary report Utility Dive · Counterparty: Southern California Edison · Bindingness not stated

    “Southern California Edison and geothermal energy company Fervo Energy announced Tuesday that they have executed two 15-year power purchase agreements for a total of 320 MW.”

    Source: Utility Dive ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  4. 12 September 2024 · Technical milestones · Whole project

    Testing reported

    30-day well test at Cape Station: flow rate and potential generation (company claim, reported by trade press); not sustained plant output

    Secondary report Utility Dive

    “A 30-day test at Cape Station achieved a maximum flow rate of 107kg/s at high temperatures, potentially enabling over 10 MW of generation, the company said.”

    Source: Utility Dive ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  5. 17 October 2024 · Permissions · Whole project

    Permission issued

    BLM approval of the Fervo Cape Geothermal Power Project (up to 2 GW; about 631 acres, 148 on public land); a federal land decision, not every permit needed to build or operate

    Regulator issued Bureau of Land Management · Authority: Bureau of Land Management · Jurisdiction: United States: federal (BLM), Beaver County, Utah

    “The Department announced that the Bureau of Land Management (BLM) has approved the Fervo Cape Geothermal Power Project in Beaver County, Utah, which will use innovative technology to generate up to 2 gigawatts (GW) of baseload power”

    Source: Bureau of Land Management ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  6. 21 October 2024 · Permissions · Whole project

    Permission issued

    Finding of No Significant Impact and decision approving the project, BLM Cedar City Field Office; 30-day appeal window

    Secondary report Utility Dive · Authority: BLM Cedar City Field Office · Jurisdiction: United States: federal (BLM), Utah

    “On Oct. 8, BLM said that its Cedar City Field Office has reached a Finding of No Significant Impacts from the project and issued a decision approving it. The 30-day period to appeal the decision will end on Nov. 7.”

    Source: Utility Dive ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  7. 17 April 2026 · Financing · Whole project

    Closed

    Project-level preferred equity in Cape Phase I HoldCo, LLC (Cape Station Phase I)

    Company reported Fervo Energy (SEC filing, Form S-1) · Counterparty: Granite Energy InvestCo, LLC ("Catalyst") · Equity · USD 100m

    “Catalyst subscribed to 4,635 Class A Units in Cape Phase I HoldCo, LLC for a total capital contribution of $100.0 million.”

    Source: Fervo Energy (SEC filing, Form S-1) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  8. 15 April 2025 · Customer / offtake · Whole project

    Agreement signed

    15-year PPA, 31 MW, Shell Energy as first offtaker from Phase I

    Company reported Fervo Energy (via Business Wire, syndicated by Silicon UK) · Counterparty: Shell Energy North America (US), L.P. · Bindingness not stated

    “today announced the execution of a 15-year power purchase agreement with Shell Energy North America (US), L.P. (“Shell Energy”) for 31 MW of 24/7 carbon-free geothermal power (the “Agreement”).”

    Source: Fervo Energy (via Business Wire, syndicated by Silicon UK) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  9. Target stated 28 June 2024 · Operational delivery · Whole project

    Target: commercial operation, 2026

    Original target (2024): initial 70 MW phase operational by 2026, next phase by 2028

    Secondary report Utility Dive

    “Fervo expects the initial 70-MW phase of the project to be operational by 2026, with the next phase coming online by 2028.”

    Source: Utility Dive ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  10. 22 June 2026 · Construction · Whole project

    Construction

    Construction of Cape Station Phase II (about 400 MW) commenced

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “Commenced construction of Cape Station Phase II in Q1 2026, which is expected to deliver approximately 400 megawatts.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  11. 12 August 2026 · Financing · Whole project

    Closed

    Project Granite: non-recourse project debt for Cape Station Phase I (closed Q1 2026; proceeds repaid the earlier XRC loan)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit) · Counterparty: Lender syndicate led by MUFG Bank (administrative agent) and HSBC Bank USA (collateral agent), per the 10-Q · Debt · About USD 421m

    “using proceeds from the Project Granite Facility, the $421 million non-recourse project debt financing for the first phase of Cape Station that Fervo closed in Q1 2026, and the XRC Facility was terminated.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  12. 12 August 2026 · Financing · Whole project

    Closed

    Cape Station, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit) · Counterparty: the Project Granite Facility · USD 421m

    “(the “XRC Facility”) using proceeds from the Project Granite Facility, the $421 million non-recourse project debt financing for the first phase of Cape Station that Fervo closed in Q1 2026, and the XRC Facility was terminated.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  13. 12 August 2026 · Commissioning · Whole project

    Commissioning

    Phase I: mechanical completion of GeoBlocks 1 and 2; GeoBlock 1 commissioning with first wells connected and turbines spinning

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “Commissioning on GeoBlock 1 continued throughout the quarter with the first set of wells having been connected to the power plant, moving geothermal brine through the heat exchangers and spinning the turbines.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  14. 12 August 2026 · Technical milestones · Whole project

    Testing reported

    Phase II drilling: Sawtooth 7 well (Fervo 3.0 design), depth, temperature and drilling time

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “During the quarter, Fervo drilled Sawtooth 7, its ninth Fervo 3.0 well, reaching a measured depth of nearly 19,500 feet in a 460°F resource in just 21 days spud-to-total-depth, a new Company record for drilling pace on its most complex well design to date.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  15. 13 August 2026 · Financing · Whole project

    Drawn / disbursed

    Amount drawn (outstanding) under the Project Granite facility as of June 30, 2026 (partial draw of about $421.4 million in commitments)

    Company reported Fervo Energy (SEC filing, Form 10-Q) · Debt · About USD 212.3m

    “As of June 30, 2026, total outstanding borrowings under the Project Granite Facility were approximately $212.3 million”

    Source: Fervo Energy (SEC filing, Form 10-Q) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  16. 12 August 2026 · Construction · GeoBlock 1

    Mechanically complete

    GeoBlock 1, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “Fervo has achieved mechanical completion on GeoBlocks 1 and 2, with mechanical completion of GeoBlock 3 expected over the coming months.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  17. 12 August 2026 · Construction · GeoBlock 2

    Mechanically complete

    GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “Fervo has achieved mechanical completion on GeoBlocks 1 and 2, with mechanical completion of GeoBlock 3 expected over the coming months.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  18. Target stated 12 August 2026 · Construction · GeoBlock 3

    Target: mechanically complete, Date not disclosed

    GeoBlock 3, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlocks 1 and 2 and progressing commissioning, with GeoBlock 3 mechanical completion expected in the coming months.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  19. 13 August 2026 · Customer / offtake · Whole project

    Agreement signed

    Phase II PPAs with SCE and Clean Power Alliance, including expansions (384 MW combined); Fervo discloses its transmission rights cover only the original contracts

    Company reported Fervo Energy (SEC filing, Form 10-Q) · Counterparty: Southern California Edison; Clean Power Alliance · Bindingness not stated

    “This capacity is sufficient to meet the obligations under our original PPAs with Southern California Edison (SCE) and Clean Power Alliance (CPA), but is insufficient to support the full 384 megawatts of combined contracted capacity with the subsequent expansions of the SCE and CPA PPAs.”

    Source: Fervo Energy (SEC filing, Form 10-Q) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  20. 13 August 2026 · Permissions · Whole project

    Permission issued

    Aggregate count: 79 of 80 government permits and approvals needed for Phase I commercial operation received, one still in process (company-reported)

    Company reported Fervo Energy (SEC filing, Form 10-Q) · Jurisdiction: United States: federal, Utah state and county (not itemised)

    “As of the date of this filing, 79 out of 80 governmental permits and approvals necessary to commence commercial operations at Cape Station Phase I have been received, with the remaining permit in process.”

    Source: Fervo Energy (SEC filing, Form 10-Q) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  21. 1 September 2026 · Customer / offtake · Whole project

    Agreement signed

    396 MW PPA for the Cape Station EGS GeoCluster expansion (expected online 2028), with an option for about 600 MW more

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit) · Counterparty: Google · Bindingness not stated

    “today announced a 396-megawatt (MW) power purchase agreement (PPA) with Google to enable the continued development of the Cape Station enhanced geothermal systems (EGS) GeoCluster, expected to come online in 2028.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  22. 1 October 2026 · Commissioning · GeoBlock 1

    Synchronised to the grid

    GeoBlock 1 (33 MW) synchronized to the grid

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “Cape Station synchronized to the grid on September 24 and declared commercial operation just six days later on September 30, one day before its contractual COD.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  23. 1 October 2026 · Operational delivery · GeoBlock 1

    Commercial operation

    GeoBlock 1 declared commercial operation (one of three Phase I GeoBlocks; one day before its contractual COD)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “Cape Station synchronized to the grid on September 24 and declared commercial operation just six days later on September 30, one day before its contractual COD.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  24. Target stated 12 August 2026 · Commissioning · Whole project

    Target: first power, Q4 2026

    Target as of August 2026: GeoBlock 1 first power in Q4 2026; GeoBlocks 2 and 3 initial power in early 2027

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlock 1 first power is targeted for the fourth quarter of 2026, with full production anticipated by year-end; GeoBlocks 2 and 3 are expected to reach initial power in early 2027.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  25. Target stated 12 August 2026 · Commissioning · GeoBlock 1

    Target: first power, Q4 2026

    GeoBlock 1, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlock 1 first power is targeted for the fourth quarter of 2026, with full production anticipated by year-end; GeoBlocks 2 and 3 are expected to reach initial power in early 2027.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  26. Target stated 12 August 2026 · Commissioning · GeoBlock 1

    Target: exporting test energy, Q4 2026

    GeoBlock 1, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “Fervo expects to begin generating test power at GeoBlock 1 in the fourth quarter of 2026, with full production anticipated by year-end.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  27. 1 October 2026 · Customer / offtake · GeoBlock 1

    Supply under contract started

    Revenue being generated under Fervo's PPA from GeoBlock 1 (offtaker not named)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit) · Bindingness not stated

    “First GeoBlock reaches contractual commercial operation date (COD) and is generating revenue under the terms of Fervo’s Power Purchase Agreement (PPA)”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  28. 1 October 2026 · Operational delivery · GeoBlock 1

    Commercial operation

    GeoBlock 1 net output at commercial operation (company-reported) and Phase I configuration

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “Cape Station's Phase I comprises approximately 100 MW across three 33-megawatt GeoBlocks. The first GeoBlock produced 33 MW of net power production, showing even in these early stages the GeoBlock is performing to expectations.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  29. 9 November 2026 · Commissioning · GeoBlock 2

    Synchronised to the grid

    GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlock 2 has achieved grid sync, a major milestone, which marks the end of hot commissioning.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  30. 9 November 2026 · Commissioning · GeoBlock 2

    Exporting test energy

    GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlock 2 has achieved grid sync and is in its early operations phase, delivering test energy to the grid.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  31. 9 November 2026 · Commissioning · GeoBlock 3

    Cold commissioning

    GeoBlock 3, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlock 3 is mechanically complete and is in cold commissioning.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  32. 9 November 2026 · Construction · GeoBlock 3

    Mechanically complete

    GeoBlock 3, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlock 3 is mechanically complete and is in cold commissioning.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  33. Target stated 12 August 2026 · Commissioning · GeoBlock 2

    Target: first power, 2027

    GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlocks 2 and 3 are expected to follow a similar sequence, with initial power in early 2027 ramping to full power over the ensuing months.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  34. Target stated 12 August 2026 · Commissioning · GeoBlock 3

    Target: first power, 2027

    GeoBlock 3, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlocks 2 and 3 are expected to follow a similar sequence, with initial power in early 2027 ramping to full power over the ensuing months.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  35. Target stated 1 October 2026 · Operational delivery · Whole project

    Target: commercial operation, Jan 1, 2027

    Target as of October 2026: GeoBlocks 2 and 3 contractual COD by January 1, 2027; Phase II (400 MW) COD in 2028

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “Commissioning continues at the remaining two Phase I GeoBlocks, which are expected to reach contractual COD by January 1, 2027. The next phase, an additional 400 MW, is already under construction, with an expected COD in 2028.”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  36. Target stated 9 November 2026 · Operational delivery · GeoBlock 2

    Target: commercial operation, Jan 1, 2027

    GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlocks 2 and 3 remain on schedule and are expected to achieve commercial operation by January 1, 2027, which will complete Cape Station”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  37. Target stated 9 November 2026 · Operational delivery · GeoBlock 3

    Target: commercial operation, Jan 1, 2027

    GeoBlock 3, as described by Fervo Energy (SEC filing, Form 8-K exhibit)

    Company reported Fervo Energy (SEC filing, Form 8-K exhibit)

    “GeoBlocks 2 and 3 remain on schedule and are expected to achieve commercial operation by January 1, 2027, which will complete Cape Station”

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

Revisions and corrections

  1. Revision 3, Nov 11, 2026, 21:17 UTC: Geoblock-2 commissioning moved from "Not established in reviewed sources" to "Exporting test energy"; geoblock-3 commissioning moved from "Not established in reviewed sources" to "Cold commissioning"; geoblock-3 construction moved from "Not established in reviewed sources" to "Mechanically complete"; 6 new source statements added.
  2. Revision 2, Nov 11, 2026, 21:16 UTC: Geoblock-1 construction moved from "Not established in reviewed sources" to "Mechanically complete"; geoblock-2 construction moved from "Not established in reviewed sources" to "Mechanically complete"; 8 new source statements added.
  3. Revision 1, Nov 11, 2026, 21:14 UTC: First published.

Earlier versions stay identifiable; nothing is silently rewritten. Spotted an error? Report a correction and we re-check the sources. Power Inflection Research is our automated research desk; the methodology explains how it works and where it stops.

Companies involved

  • Fervo Energy, developer (public (frvo))
  • Southern California Edison: Customer: two 15-year power purchase agreements, 320 MW (June 2024)
  • Clean Power Alliance: Customer: power purchase agreement, original plus expansion (per Fervo's 10-Q)
  • Shell Energy North America: Customer: 15-year power purchase agreement, 31 MW from Phase I (April 2025)
  • Google: Customer: 396 MW power purchase agreement for the Cape Station GeoCluster expansion (September 2026)
  • MUFG Bank: Administrative agent, Project Granite construction-to-term debt for Phase I
  • HSBC Bank USA: Collateral agent, Project Granite construction-to-term debt for Phase I
  • Granite Energy InvestCo: Project-level preferred equity in Cape Phase I HoldCo (named "Catalyst" in Fervo's S-1)

Linked names are companies we follow. A listed partner is not a way to own the developer; investment access is shown per company, with its source.