Project: permissionsSecondary report
What was reported
On Oct. 8, BLM said that its Cedar City Field Office has reached a Finding of No Significant Impacts from the project and issued a decision approving it. The 30-day period to appeal the decision will end on Nov. 7.Regulator, government, developer and customer statements named in the Project Ledger · Utility Dive statement · Oct 21, 2024 · Open the source ↗
What the evidence supports
That Utility Dive, a secondary source, published the quoted statement. It records "permission issued" for Finding of No Significant Impact and decision approving the project, BLM Cedar City Field Office; 30-day appeal window under permissions only.
What remains unknown
One permission is not every permission the project needs. Any permission beyond the action quoted. A construction authorisation is not an operating licence, and one authority's action is not another's.
Source passages
Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.
Utility Dive statementOn Oct. 8, BLM said that its Cedar City Field Office has reached a Finding of No Significant Impacts from the project and issued a decision approving it. The 30-day period to appeal the decision will end on Nov. 7.Regulator, government, developer and customer statements named in the Project Ledger · Utility Dive statement · Oct 21, 2024 · Open the source ↗
Revision history
- Revision 1 · Nov 11, 2026, 21:13 UTC
Cape Station: Finding of No Significant Impact and decision approving the project, BLM Cedar City Field Office; 30-day appeal window (permission issued)
Spotted an error? Tell us. Corrections are published, never silent: see all corrections.