| 9 November 2026 | Cape Station GeoBlock 2 | Commissioning | Synchronised to the grid: GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit) | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 9 November 2026 | Cape Station GeoBlock 2 | Commissioning | Exporting test energy: GeoBlock 2, as described by Fervo Energy (SEC filing, Form 8-K exhibit) | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 9 November 2026 | Cape Station GeoBlock 2 | Operational delivery | Target: commercial operation, Jan 1, 2027 | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 9 November 2026 | Cape Station GeoBlock 3 | Commissioning | Cold commissioning: GeoBlock 3, as described by Fervo Energy (SEC filing, Form 8-K exhibit) | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 9 November 2026 | Cape Station GeoBlock 3 | Construction | Mechanically complete: GeoBlock 3, as described by Fervo Energy (SEC filing, Form 8-K exhibit) | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 9 November 2026 | Cape Station GeoBlock 3 | Operational delivery | Target: commercial operation, Jan 1, 2027 | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 1 October 2026 | Cape Station GeoBlock 1 | Customer / offtake | Supply under contract started: Revenue being generated under Fervo's PPA from GeoBlock 1 (offtaker not named) | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 1 October 2026 | Cape Station GeoBlock 1 | Commissioning | Synchronised to the grid: GeoBlock 1 (33 MW) synchronized to the grid | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 1 October 2026 | Cape Station GeoBlock 1 | Operational delivery | Commercial operation: GeoBlock 1 declared commercial operation (one of three Phase I GeoBlocks; one day before its contractual COD) | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 1 October 2026 | Cape Station GeoBlock 1 | Operational delivery | Commercial operation: GeoBlock 1 net output at commercial operation (company-reported) and Phase I configuration | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 1 October 2026 | Cape Station | Operational delivery | Target: commercial operation, Jan 1, 2027 | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 21 September 2026 | Hermes 2 Demonstration Plant | Financing | Conditional: Samsung C&T strategic investment in Kairos Power (company level), binding term sheet, subject to regulatory approvals; stated purpose is Hermes 2 delivery | Joint release · Kairos Power ↗ |
|---|
| 1 September 2026 | Cape Station | Customer / offtake | Agreement signed: 396 MW PPA for the Cape Station EGS GeoCluster expansion (expected online 2028), with an option for about 600 MW more | Company reported · Fervo Energy (SEC filing, Form 8-K exhibit) ↗ |
|---|
| 20 August 2026 | Long Mott Generating Station | Permissions | Application accepted for review: NRC notices the mandatory (uncontested) hearing on the construction permit application, set for September 22, 2026 (application still under review) | Regulator issued · U.S. Nuclear Regulatory Commission (Federal Register, via govinfo.gov) ↗ |
|---|
| 20 August 2026 | Long Mott Generating Station | Technical milestones | Design disclosed: Plant configuration as described by the NRC: four Xe-100 reactors, 800 MW thermal | Regulator issued · U.S. Nuclear Regulatory Commission (Federal Register, via govinfo.gov) ↗ |
|---|
| 13 August 2026 | Cape Station | Customer / offtake | Agreement signed: Phase II PPAs with SCE and Clean Power Alliance, including expansions (384 MW combined); Fervo discloses its transmission rights cover only the original contracts | Company reported · Fervo Energy (SEC filing, Form 10-Q) ↗ |
|---|
| 13 August 2026 | Cape Station | Financing | Drawn / disbursed: Amount drawn (outstanding) under the Project Granite facility as of June 30, 2026 (partial draw of about $421.4 million in commitments) | Company reported · Fervo Energy (SEC filing, Form 10-Q) ↗ |
|---|
| 13 August 2026 | Cape Station | Permissions | Permission issued: Aggregate count: 79 of 80 government permits and approvals needed for Phase I commercial operation received, one still in process (company-reported) | Company reported · Fervo Energy (SEC filing, Form 10-Q) ↗ |
|---|
| 13 August 2026 | Long Mott Generating Station | Customer / offtake | Agreement signed: Master Project Development Agreement with Dow, continuing the 2023 joint development agreement | Company reported · X-energy (SEC Form 10-Q, Q2 2026) ↗ |
|---|
| 13 August 2026 | Long Mott Generating Station | Operational delivery | Target: commercial operation, Date not disclosed | Company reported · X-energy (SEC Form 10-Q, Q2 2026) ↗ |
|---|
| 13 August 2026 | Long Mott Generating Station | Financing | Announced: Funding responsibility for building the plant: Dow funds it and is eligible for 50% ARDP reimbursement | Company reported · X-energy (SEC Form 10-Q, Q2 2026) ↗ |
|---|
| 13 August 2026 | Long Mott Generating Station | Financing | Drawn / disbursed: Cumulative ARDP reimbursements to X-energy as of June 30, 2026 (whole award: plant and TX-1 fuel facility work) | Company reported · X-energy (SEC Form 10-Q, Q2 2026) ↗ |
|---|
| 13 August 2026 | Long Mott Generating Station | Financing | Closed: DOE approves ARDP continuation application: budget period extended through March 2027 | Company reported · X-energy (SEC filing) ↗ |
|---|
| 13 August 2026 | Long Mott Generating Station | Financing | Conditional: Additional ARDP allocation to X-energy: selected, but subject to a contract modification and continuation approvals (amount not stated) | Company reported · X-energy (SEC Form 10-Q, Q2 2026) ↗ |
|---|
| 13 August 2026 | Long Mott Generating Station | Permissions | Target: permission issued, Q1 2027 | Company reported · X-energy (SEC Form 10-Q, Q2 2026) ↗ |
|---|