Seven dimensions, each with its own evidence

Where it stands, by unit and by dimension.

A grid-connected demonstration plant for Kairos Power's fluoride salt-cooled reactor, licensed by the NRC in 2024 as a two-unit test reactor facility. In 2025 Kairos said it would instead build a single, larger reactor of about 50 MWe, whose output TVA has agreed to buy. Each dimension shows its latest sourced state for the scope you choose. A unit never inherits another unit’s progress, and nothing here adds up to a score.

Financing · Hermes 2 Demonstration Plant, whole project

Conditional

Samsung C&T strategic investment in Kairos Power (company level), binding term sheet, subject to regulatory approvals; stated purpose is Hermes 2 delivery

Conditional is not final.

Joint release Kairos Power · Disclosed 21 September 2026

“Samsung C&T has agreed to provide up to $100 million through a combination of direct investment and in-kind engineering services, subject to regulatory approvals, to enable the successful delivery of the Hermes 2 Demonstration Plant in Oak Ridge, Tennessee.”

Inspect primary source: Kairos Power ↗

Open question

Which money is proposed, conditional, closed or actually drawn, and for what?

  • Not established in reviewed sources: Project cost
  • Not established in reviewed sources: Closing of the Samsung C&T investment (term sheet is subject to regulatory approvals)
  • Not established in reviewed sources: Any government funding specific to Hermes 2
  • Not established in reviewed sources: Project-level debt
Statements on record here (1)
  1. Conditional: Samsung C&T strategic investment in Kairos Power (company level), binding term sheet, subject to regulatory approvals; stated purpose is Hermes 2 delivery Joint release · Kairos Power · 21 September 2026 · Source ↗

Open this dimension in the ledger →Watch financing

“Not established in reviewed sources” means the sources we reviewed do not say. It is not zero, a failure or a negative finding.

Quantities in context

Per reactor, original dual-unit concept
14 MWeTarget: planned rating, not measured output
Redesigned single-reactor plant
50 MWeTarget: planned rating, not measured output
Up to 50 MW delivered to TVA under the PPA
50 MWTarget: planned rating, not measured output · exported
Per reactor, original two-unit design
35 MWthTarget: planned rating, not measured output

MW is power and MWh is energy; thermal (MWth) is not electrical (MWe). A planned rating says nothing about electricity generated. No capacity factor, readiness percentage or return is calculated here.

Stated targets

  • Target: construction, July 2025, per World Nuclear News, stated 25 July 2023. Source ↗
  • Target: commercial operation, 2030, per Kairos Power, stated 18 August 2025. Source ↗

A target is what a party said it aims for, kept with the date it said it. It never sets a state. When a target moves, both versions stay on record.

Scoped alerts

Hear when this record changes.

Follow the whole project, one unit, or one dimension of one unit. You confirm the choice after signing in; nothing is followed until you do. Each briefing gives the previous state, the new state and the source.

To watch a single dimension, choose it above and use its watch link. Monitoring is part of Pro, $49/month. Reading every record stays free.

Explore the sampleGet the weekly briefing

Project history

Every statement on record, oldest first.

Quoted exactly and dated only as precisely as the source. Copies of one release count as one origin. A withdrawn statement stays visible and is labelled.

  1. 4 August 2023 · Permissions · Whole project

    Application submitted

    Construction permit application, two-unit Hermes 2 facility

    Regulator issued U.S. Nuclear Regulatory Commission (Federal Register) · Authority: U.S. Nuclear Regulatory Commission · Jurisdiction: United States (federal)

    “The U.S. Nuclear Regulatory Commission (NRC) is providing public notice of receipt and availability of an application for construction permits for a two-unit reactor facility from Kairos Power, LLC. The application for the construction permits was received on July 14, 2023.”

    Source: U.S. Nuclear Regulatory Commission (Federal Register) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  2. 15 September 2023 · Permissions · Whole project

    Application accepted for review

    Construction permit application accepted for docketing (Docket Nos. 50-611 and 50-612)

    Regulator issued U.S. Nuclear Regulatory Commission (Federal Register) · Authority: U.S. Nuclear Regulatory Commission · Jurisdiction: United States (federal)

    “The U.S. Nuclear Regulatory Commission (NRC) staff accepts and dockets an application for a construction permit for the Hermes 2 test reactor facility to be built in Oak Ridge, Tennessee. DATES: This action becomes effective on September 11, 2023.”

    Source: U.S. Nuclear Regulatory Commission (Federal Register) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  3. 15 September 2023 · Technical milestones · Whole project

    Design disclosed

    Hermes 2 design as described in the NRC docketing notice (original two-unit design)

    Regulator issued U.S. Nuclear Regulatory Commission (Federal Register)

    “The Hermes 2 facility would contain two fluoride-salt cooled, high- temperature reactors that use solid tri-structural isotropic fuel in pebble form, intermediate liquid-sodium loops, and a common power conversion unit.”

    Source: U.S. Nuclear Regulatory Commission (Federal Register) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  4. 10 January 2024 · Technical milestones · Whole project

    Testing reported

    Non-nuclear Engineering Test Unit (ETU), same KP-FHR technology, Albuquerque; not Hermes 2 hardware

    Company reported Kairos Power

    “Kairos Power has successfully completed 1,000 hours of pumped salt operations with its non-nuclear Engineering Testing Unit (ETU) at the company’s testing and manufacturing facility in Albuquerque, N.M.”

    Source: Kairos Power ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  5. 14 October 2024 · Customer / offtake · Whole project

    Agreement signed

    Google–Kairos Master Plant Development Agreement for a 500 MW fleet by 2035 (this release does not name Hermes 2; later releases call Hermes 2 its first deployment)

    Joint release Kairos Power · Counterparty: Google · Bindingness not stated

    “Kairos Power and Google have signed a Master Plant Development Agreement, creating a path to deploy a U.S. fleet of advanced nuclear power projects totaling 500 MW by 2035.”

    Source: Kairos Power ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  6. 29 November 2024 · Permissions · Whole project

    Permission issued

    Construction permits CPTR-7 and CPTR-8, two units of the Hermes 2 test reactor facility (not an operating licence)

    Regulator issued U.S. Nuclear Regulatory Commission (Federal Register) · Authority: U.S. Nuclear Regulatory Commission · Jurisdiction: United States (federal)

    “The U.S. Nuclear Regulatory Commission (NRC) is providing notice of the issuance of Construction Permits CPTR-7 and CPTR-8 to Kairos Power LLC (Kairos) for the two units of the proposed Hermes 2 test reactor facility. DATES: The Construction Permits CPTR-7 and CPTR-8 were issued on November 21, 2024.”

    Source: U.S. Nuclear Regulatory Commission (Federal Register) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  7. 2025 · Customer / offtake · Whole project

    Agreement signed

    TVA's annual report statement of the Hermes 2 PPA

    Customer statement Tennessee Valley Authority (annual report, Form 10-K, FY2025) · Counterparty: Tennessee Valley Authority (TVA) · Bindingness not stated

    “In 2025, TVA signed a PPA to purchase up to 50 MW of electricity from the Kairos Power Hermes 2 Plant in Oak Ridge, Tennessee.”

    Source: Tennessee Valley Authority (annual report, Form 10-K, FY2025) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  8. Target stated 25 July 2023 · Construction · Whole project

    Target: construction, July 2025

    Original schedule in the 2023 construction permit application (earliest construction start; first unit completion July–December 2027)

    Secondary report World Nuclear News

    “According to the application, the earliest start date for construction of Hermes 2 is expected to be July 2025 with the first unit projected to be completed by July 2027 at the earliest and December 2027 at the latest.”

    Source: World Nuclear News ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  9. 18 August 2025 · Customer / offtake · Whole project

    Agreement signed

    Power purchase agreement, Kairos Power and TVA, Hermes 2 output (Google receives the clean energy attributes)

    Joint release Kairos Power · Counterparty: Tennessee Valley Authority (TVA) · Bindingness not stated

    “Through a new power purchase agreement (PPA) between Kairos Power and TVA, Kairos Power’s Hermes 2 Plant in Oak Ridge, Tenn., will deliver up to 50 megawatts (MW) of reliable, 24/7 energy to the TVA grid that powers Google data centers in Tennessee and Alabama.”

    Source: Kairos Power ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  10. 18 August 2025 · Customer / offtake · Whole project

    Agreement signed

    Google's account of the Hermes 2 PPA between Kairos Power and TVA

    Customer statement Google (blog) · Counterparty: Tennessee Valley Authority (TVA); Google · Bindingness not stated

    “Today we announced the first deployment of Kairos Power’s advanced nuclear reactor — the Hermes 2 Plant in Oak Ridge, Tennessee — through a new power purchase agreement (PPA) between Kairos Power and Tennessee Valley Authority (TVA).”

    Source: Google (blog) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  11. 21 October 2025 · Technical milestones · Whole project

    Design disclosed

    Redesign: one 50 MWe reactor in place of the original two-unit plant

    Company reported Kairos Power (newsletter)

    “To accelerate our mission, we are enlarging Hermes 2 to a 50 MWe plant powered by a single commercial-scale reactor – a step change in scale from the smaller 14 MWe reactors envisioned in the original dual-unit plant concept.”

    Source: Kairos Power (newsletter) ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  12. 23 May 2026 · Construction · Whole project

    Site work

    DOE account of the Hermes 2 groundbreaking (separate from Hermes 1 nuclear construction)

    Government record U.S. Department of Energy, Office of Nuclear Energy

    “Kairos Power initiated nuclear construction on their Hermes test reactor in May 2025 and broke ground on their Hermes 2 reactor in April 2026.”

    Source: U.S. Department of Energy, Office of Nuclear Energy ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  13. 17 April 2026 · Construction · Whole project

    Site work

    Groundbreaking on Hermes 2 (Kairos calls it the start of construction; nuclear safety-related construction not reported)

    Company reported Kairos Power

    “Today, Kairos Power broke ground on the Hermes 2 Demonstration Plant in Oak Ridge, Tenn. – the company’s first commercial-scale reactor and the first-ever power-producing Gen IV reactor to receive a construction permit from the Nuclear Regulatory Commission (NRC).”

    Source: Kairos Power ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  14. 21 September 2026 · Financing · Whole project

    Conditional

    Samsung C&T strategic investment in Kairos Power (company level), binding term sheet, subject to regulatory approvals; stated purpose is Hermes 2 delivery

    Joint release Kairos Power · Counterparty: Samsung C&T Engineering & Construction Group · Other instrument · Up to USD 100m

    “Samsung C&T has agreed to provide up to $100 million through a combination of direct investment and in-kind engineering services, subject to regulatory approvals, to enable the successful delivery of the Hermes 2 Demonstration Plant in Oak Ridge, Tennessee.”

    Source: Kairos Power ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

  15. Target stated 18 August 2025 · Operational delivery · Whole project

    Target: commercial operation, 2030

    Start of operations of the redesigned single-reactor Hermes 2 (stated as 'begin operations')

    Joint release Kairos Power

    “To accelerate the delivery of clean energy to Google, Kairos Power will increase Hermes 2’s output from 28 MW to 50 MW generated by a single reactor, scheduled to begin operations in 2030.”

    Source: Kairos Power ↗ · Open in the ledger · What this does and does not establish · source read 11 November 2026

Revisions and corrections

  1. Revision 1, Nov 11, 2026, 21:12 UTC: First published.

Earlier versions stay identifiable; nothing is silently rewritten. Spotted an error? Report a correction and we re-check the sources. Power Inflection Research is our automated research desk; the methodology explains how it works and where it stops.

Companies involved

  • Kairos Power, developer (ownership not confirmed)
  • Tennessee Valley Authority: Power purchaser (PPA for up to 50 MW from Hermes 2)
  • Google: Receives the plant's clean energy attributes through TVA; Hermes 2 is the first deployment under its Master Plant Development Agreement with Kairos Power
  • Samsung C&T: Strategic investor in Kairos Power (binding term sheet, up to $100 million, subject to regulatory approvals) and EPC team member for Hermes 2
  • Barnard Construction: General contractor for both Hermes reactor projects