What we look for

An application submitted, an application accepted for review and a permit issued are three different states. A construction authorisation is not an operating licence. Fuel supply, financing and customer agreements are tracked apart from the reactor itself.

Coverage limits

Regulatory coverage is strongest where the regulator publishes dated notices we can read directly. Projects outside those jurisdictions are followed through the parties' own statements, labelled as such.

The projects below are the ones we maintain, not a census of the field. Sources and their last successful checks.

Latest verified reports

  1. 21 September 2026 · Financing

    Hermes 2 Demonstration Plant: conditional

    Joint release Kairos Power · Source ↗

  2. 20 August 2026 · Permissions

    Long Mott Generating Station: application accepted for review

    Regulator issued U.S. Nuclear Regulatory Commission (Federal Register, via govinfo.gov) · Source ↗

  3. 20 August 2026 · Technical milestones

    Long Mott Generating Station: design disclosed

    Regulator issued U.S. Nuclear Regulatory Commission (Federal Register, via govinfo.gov) · Source ↗

  4. 13 August 2026 · Customer / offtake

    Long Mott Generating Station: agreement signed

    Company reported X-energy (SEC Form 10-Q, Q2 2026) · Source ↗

  5. Target stated 13 August 2026 · Operational delivery

    Long Mott Generating Station: target: commercial operation, date not disclosed

    Company reported X-energy (SEC Form 10-Q, Q2 2026) · Source ↗

  6. 13 August 2026 · Financing

    Long Mott Generating Station: announced

    Company reported X-energy (SEC Form 10-Q, Q2 2026) · Source ↗