Project: commissioningCompany-reported

What was reported

GeoBlock 3 is mechanically complete and is in cold commissioning.U.S. Securities and Exchange Commission (EDGAR) · Exhibit 99.1 to 8-K · Nov 9, 2026 · Open the source ↗

What the evidence supports

That Fervo Energy (SEC filing, Form 8-K exhibit), the project's developer, published the quoted statement. It records "cold commissioning" for GeoBlock 3, as described by Fervo Energy (SEC filing, Form 8-K exhibit) under commissioning only. It applies to GeoBlock 3 only, not to the project's other units.

What remains unknown

Cold commissioning comes before any power is produced. Commercial operation. A test, a synchronisation or test energy is not contracted delivery, and says nothing about another unit.

Source passages

Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.

Fervo Energy (SEC filing, Form 8-K exhibit) statementGeoBlock 3 is mechanically complete and is in cold commissioning.U.S. Securities and Exchange Commission (EDGAR) · Exhibit 99.1 to 8-K · Nov 9, 2026 · Open the source ↗

Revision history

  1. Revision 1 · Nov 11, 2026, 21:17 UTC

    Cape Station GeoBlock 3: cold commissioning (company reported)