Project: operational deliveryCompany-reported

What was reported

Cape Station's Phase I comprises approximately 100 MW across three 33-megawatt GeoBlocks. The first GeoBlock produced 33 MW of net power production, showing even in these early stages the GeoBlock is performing to expectations.Regulator, government, developer and customer statements named in the Project Ledger · Fervo Energy (SEC filing, Form 8-K exhibit) statement · Oct 1, 2026 · Open the source ↗

What the evidence supports

That Fervo Energy (SEC filing, Form 8-K exhibit), the project's developer, published the quoted statement. It records "commercial operation" for GeoBlock 1 net output at commercial operation (company-reported) and Phase I configuration under operational delivery only. It applies to GeoBlock 1 only, not to the project's other units.

What remains unknown

Commercial operation says nothing about performance or returns. Performance over time, returns, or the status of any other unit, unless the quoted passage states them.

Source passages

Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.

Fervo Energy (SEC filing, Form 8-K exhibit) statementCape Station's Phase I comprises approximately 100 MW across three 33-megawatt GeoBlocks. The first GeoBlock produced 33 MW of net power production, showing even in these early stages the GeoBlock is performing to expectations.Regulator, government, developer and customer statements named in the Project Ledger · Fervo Energy (SEC filing, Form 8-K exhibit) statement · Oct 1, 2026 · Open the source ↗

Revision history

  1. Revision 1 · Nov 11, 2026, 21:14 UTC

    Cape Station GeoBlock 1: GeoBlock 1 net output at commercial operation (company-reported) and Phase I configuration (commercial operation)

Spotted an error? Tell us. Corrections are published, never silent: see all corrections.