What was reported
As of the date of this filing, 79 out of 80 governmental permits and approvals necessary to commence commercial operations at Cape Station Phase I have been received, with the remaining permit in process.Regulator, government, developer and customer statements named in the Project Ledger · Fervo Energy (SEC filing, Form 10-Q) statement · Aug 13, 2026 · Open the source ↗
What the evidence supports
That Fervo Energy (SEC filing, Form 10-Q), the project's developer, published the quoted statement. It records "permission issued" for Aggregate count: 79 of 80 government permits and approvals needed for Phase I commercial operation received, one still in process (company-reported) under permissions only.
What remains unknown
One permission is not every permission the project needs. Any permission beyond the action quoted. A construction authorisation is not an operating licence, and one authority's action is not another's.
Source passages
Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.
Fervo Energy (SEC filing, Form 10-Q) statementAs of the date of this filing, 79 out of 80 governmental permits and approvals necessary to commence commercial operations at Cape Station Phase I have been received, with the remaining permit in process.Regulator, government, developer and customer statements named in the Project Ledger · Fervo Energy (SEC filing, Form 10-Q) statement · Aug 13, 2026 · Open the source ↗
Revision history
- Revision 1 · Nov 11, 2026, 21:14 UTC
Cape Station: Aggregate count: 79 of 80 government permits and approvals needed for Phase I commercial operation received, one still in process (company-reported) (permission issued)
Spotted an error? Tell us. Corrections are published, never silent: see all corrections.