Cape Station GeoBlock 2: exporting test energy (company reported)
“GeoBlock 2 has achieved grid sync and is in its early operations phase, delivering test energy to the grid.”
Matches a theme you follow · Company-reported
Cape Station GeoBlock 2: synchronised to the grid (company reported)
“GeoBlock 2 has achieved grid sync, a major milestone, which marks the end of hot commissioning.”
Matches a theme you follow · Company-reported
Cape Station GeoBlock 3: mechanically complete (company reported)
Matches a theme you follow · Company-reported
Cape Station GeoBlock 2: commercial operation targeted for Jan 1, 2027
“GeoBlocks 2 and 3 remain on schedule and are expected to achieve commercial operation by January 1, 2027, which will complete Cape Station”
Matches a theme you follow · Company-reported
Cape Station GeoBlock 3: cold commissioning (company reported)
Matches a theme you follow · Company-reported
Cape Station GeoBlock 3: commercial operation targeted for Jan 1, 2027
“GeoBlocks 2 and 3 remain on schedule and are expected to achieve commercial operation by January 1, 2027, which will complete Cape Station”
Matches a theme you follow · Company-reported
Week of Sep 28 · 4 items
Cape Station GeoBlock 1: GeoBlock 1 net output at commercial operation (company-reported) and Phase I configuration (commercial operation)
“Cape Station's Phase I comprises approximately 100 MW across three 33-megawatt GeoBlocks. The first GeoBlock produced 33 MW of net power production, showing even in these early stages the GeoBlock is performing to expectations.”
Matches a theme you follow · Company-reported
Cape Station GeoBlock 1: Revenue being generated under Fervo's PPA from GeoBlock 1 (offtaker not named) (supply under contract started)
“First GeoBlock reaches contractual commercial operation date (COD) and is generating revenue under the terms of Fervo’s Power Purchase Agreement (PPA)”
Matches a theme you follow · Company-reported
Cape Station: commercial operation targeted for Jan 1, 2027
“Commissioning continues at the remaining two Phase I GeoBlocks, which are expected to reach contractual COD by January 1, 2027. The next phase, an additional 400 MW, is already under construction, with an expected COD in 2028.”
Matches a theme you follow · Company-reported
Cape Station GeoBlock 1: GeoBlock 1 declared commercial operation (one of three Phase I GeoBlocks; one day before its contractual COD) (commercial operation)
“Cape Station synchronized to the grid on September 24 and declared commercial operation just six days later on September 30, one day before its contractual COD.”
Matches a theme you follow · Company-reported
Week of Sep 21 · 1 item
Cape Station GeoBlock 1: GeoBlock 1 (33 MW) synchronized to the grid (synchronised to the grid)
“Cape Station synchronized to the grid on September 24 and declared commercial operation just six days later on September 30, one day before its contractual COD.”
Matches a theme you follow · Company-reported
Week of Aug 31 · 1 item
Cape Station: 396 MW PPA for the Cape Station EGS GeoCluster expansion (expected online 2028), with an option for about 600 MW more (agreement signed)
“today announced a 396-megawatt (MW) power purchase agreement (PPA) with Google to enable the continued development of the Cape Station enhanced geothermal systems (EGS) GeoCluster, expected to come online in 2028.”
Matches a theme you follow · Company-reported
Week of Aug 10 · 2 items
Cape Station: Aggregate count: 79 of 80 government permits and approvals needed for Phase I commercial operation received, one still in process (company-reported) (permission issued)
“As of the date of this filing, 79 out of 80 governmental permits and approvals necessary to commence commercial operations at Cape Station Phase I have been received, with the remaining permit in process.”
Matches a theme you follow · Company-reported
Cape Station: Phase II PPAs with SCE and Clean Power Alliance, including expansions (384 MW combined); Fervo discloses its transmission rights cover only the original contracts (agreement signed)
“This capacity is sufficient to meet the obligations under our original PPAs with Southern California Edison (SCE) and Clean Power Alliance (CPA), but is insufficient to support the full 384 megawatts of combined contracted capacity with the…”
Matches a theme you follow · Company-reported
8 of the last 13 weeks had nothing for this watchlist; those digests would have said so plainly.
Some sources are currently behind schedule; recent weeks may be incomplete.