Project: customer / offtakeCompany-reported

What was reported

First GeoBlock reaches contractual commercial operation date (COD) and is generating revenue under the terms of Fervo’s Power Purchase Agreement (PPA)Regulator, government, developer and customer statements named in the Project Ledger · Fervo Energy (SEC filing, Form 8-K exhibit) statement · Oct 1, 2026 · Open the source ↗

What the evidence supports

That Fervo Energy (SEC filing, Form 8-K exhibit), the project's developer, published the quoted statement. It records "supply under contract started" for Revenue being generated under Fervo's PPA from GeoBlock 1 (offtaker not named) under customer / offtake only. It applies to GeoBlock 1 only, not to the project's other units. Bindingness not stated.

What remains unknown

Supply started; volumes over time not established. Delivered volumes, recognised revenue or binding terms, unless the quoted passage states them.

Source passages

Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.

Fervo Energy (SEC filing, Form 8-K exhibit) statementFirst GeoBlock reaches contractual commercial operation date (COD) and is generating revenue under the terms of Fervo’s Power Purchase Agreement (PPA)Regulator, government, developer and customer statements named in the Project Ledger · Fervo Energy (SEC filing, Form 8-K exhibit) statement · Oct 1, 2026 · Open the source ↗

Revision history

  1. Revision 1 · Nov 11, 2026, 21:14 UTC

    Cape Station GeoBlock 1: Revenue being generated under Fervo's PPA from GeoBlock 1 (offtaker not named) (supply under contract started)

Spotted an error? Tell us. Corrections are published, never silent: see all corrections.