Project: stated targetCompany-reported

What was reported

GeoBlocks 2 and 3 are expected to follow a similar sequence, with initial power in early 2027 ramping to full power over the ensuing months.U.S. Securities and Exchange Commission (EDGAR) · Exhibit 99.1 to 8-K · Aug 12, 2026 · Open the source ↗

What the evidence supports

That Fervo Energy (SEC filing, Form 8-K exhibit), the project's developer, published the quoted statement. It records a target, not something that has happened. Targets can move; earlier and later targets are both kept.

What remains unknown

Whether the target will be met. Commercial operation. A test, a synchronisation or test energy is not contracted delivery, and says nothing about another unit.

Source passages

Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.

Fervo Energy (SEC filing, Form 8-K exhibit) statementGeoBlocks 2 and 3 are expected to follow a similar sequence, with initial power in early 2027 ramping to full power over the ensuing months.U.S. Securities and Exchange Commission (EDGAR) · Exhibit 99.1 to 8-K · Aug 12, 2026 · Open the source ↗

Revision history

  1. Revision 1 · Nov 11, 2026, 21:16 UTC

    Cape Station GeoBlock 3: first power targeted for 2027

Spotted an error? Tell us. Corrections are published, never silent: see all corrections.