Evidence detail
Permission issued
Aggregate count: 79 of 80 government permits and approvals needed for Phase I commercial operation received, one still in process (company-reported)
One permission is not every permission the project needs.
“As of the date of this filing, 79 out of 80 governmental permits and approvals necessary to commence commercial operations at Cape Station Phase I have been received, with the remaining permit in process.”
- Attribution
- Company reported
- Publisher
- Fervo Energy (SEC filing, Form 10-Q)
- Dated
- 13 August 2026
- First public disclosure
- 13 August 2026
- State before
- Not established in reviewed sources
- Jurisdiction
- United States: federal, Utah state and county (not itemised)
- Source read
- 11 November 2026
Inspect primary source: Fervo Energy (SEC filing, Form 10-Q) ↗
What this does and does not establish
An exact passage match shows the source says this. It does not prove the underlying claim is true.