Evidence detail

Target: construction, Date not disclosed

Revised at permit filing: construction "later this decade", start-up "early next decade"

A stated target, not something that has happened. It does not set a state. Targets can move; earlier and later ones are both kept.

“The proposed project could begin construction later this decade and start up early next decade.”
Attribution
Joint release
Publisher
Dow and X-energy (joint release, Dow newsroom)
Target stated
31 March 2025
First public disclosure
31 March 2025
Source read
11 November 2026

Inspect primary source: Dow and X-energy (joint release, Dow newsroom) ↗

What this does and does not establish

An exact passage match shows the source says this. It does not prove the underlying claim is true.

Watch constructionInspect project history

Long Mott Generating Station: ledger · Power Inflection