Testing reported
Phase II drilling: Sawtooth 7 well (Fervo 3.0 design), depth, temperature and drilling time
Test results stay attributed to whoever reported them.
“During the quarter, Fervo drilled Sawtooth 7, its ninth Fervo 3.0 well, reaching a measured depth of nearly 19,500 feet in a 460°F resource in just 21 days spud-to-total-depth, a new Company record for drilling pace on its most complex well design to date.”
- Attribution
- Company reported
- Publisher
- Fervo Energy (SEC filing, Form 8-K exhibit)
- Dated
- 12 August 2026
- First public disclosure
- 12 August 2026
- State before
- Not established in reviewed sources
- Source read
- 11 November 2026
Inspect primary source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗
What this does and does not establish
An exact passage match shows the source says this. It does not prove the underlying claim is true.