State

Not established in reviewed sources

Open question

Is this unit in contracted commercial operation, and what delivery or interruption is on record?

  • Not established in reviewed sources: Independent confirmation of the September 2026 grid synchronization and commercial operation
  • Not established in reviewed sources: Whether GeoBlocks 2 and 3 met the January 1, 2027 contractual date
  1. TargetTarget: commercial operation, Jan 1, 2027Stated 1 October 2026 · Company reported · Fervo Energy (SEC filing, Form 8-K exhibit)

    Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗

  2. TargetTarget: commercial operation, 2026Stated 28 June 2024 · Secondary report · Utility Dive

    Source: Utility Dive ↗

Evidence detail

Target: commercial operation, 2026

Original target (2024): initial 70 MW phase operational by 2026, next phase by 2028

A stated target, not something that has happened. It does not set a state. Targets can move; earlier and later ones are both kept.

“Fervo expects the initial 70-MW phase of the project to be operational by 2026, with the next phase coming online by 2028.”
Attribution
Secondary report
Publisher
Utility Dive
Target stated
28 June 2024
First public disclosure
28 June 2024
Source read
11 November 2026

Inspect primary source: Utility Dive ↗

What this does and does not establish

An exact passage match shows the source says this. It does not prove the underlying claim is true.

Watch operational deliveryInspect project history