State

Agreement signed

Capacity under contract is not energy supplied.

Open question

Who has committed to buy the output, on what stated terms, and has any energy been supplied?

  • Not established in reviewed sources: Contract prices for any Cape Station PPA
  • Not established in reviewed sources: Which offtaker receives GeoBlock 1's output first under commercial operation
  • Not established in reviewed sources: Whether the Google PPA has received the regulatory approvals it references
  1. Current stateAgreement signed1 September 2026 · Company reported · Fervo Energy (SEC filing, Form 8-K exhibit)

    Before: Not established in reviewed sources. Source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗

  2. Earlier statementAgreement signed13 August 2026 · Company reported · Fervo Energy (SEC filing, Form 10-Q)

    Before: Not established in reviewed sources. Source: Fervo Energy (SEC filing, Form 10-Q) ↗

  3. Earlier statementAgreement signed15 April 2025 · Company reported · Fervo Energy (via Business Wire, syndicated by Silicon UK)

    Before: Not established in reviewed sources. Source: Fervo Energy (via Business Wire, syndicated by Silicon UK) ↗

  4. Earlier statementAgreement signed28 June 2024 · Secondary report · Utility Dive

    Before: Not established in reviewed sources. Source: Utility Dive ↗

Evidence detail

Agreement signed

Phase II PPAs with SCE and Clean Power Alliance, including expansions (384 MW combined); Fervo discloses its transmission rights cover only the original contracts

Capacity under contract is not energy supplied.

“This capacity is sufficient to meet the obligations under our original PPAs with Southern California Edison (SCE) and Clean Power Alliance (CPA), but is insufficient to support the full 384 megawatts of combined contracted capacity with the subsequent expansions of the SCE and CPA PPAs.”
Attribution
Company reported
Publisher
Fervo Energy (SEC filing, Form 10-Q)
Dated
13 August 2026
First public disclosure
13 August 2026
State before
Not established in reviewed sources
Counterparty
Southern California Edison; Clean Power Alliance
Detail
Bindingness not stated
Source read
11 November 2026

Inspect primary source: Fervo Energy (SEC filing, Form 10-Q) ↗

What this does and does not establish

An exact passage match shows the source says this. It does not prove the underlying claim is true.

Watch customer / offtakeInspect project history