Evidence detail
Commissioning
Phase I: mechanical completion of GeoBlocks 1 and 2; GeoBlock 1 commissioning with first wells connected and turbines spinning
Commissioning is not commercial operation.
“Commissioning on GeoBlock 1 continued throughout the quarter with the first set of wells having been connected to the power plant, moving geothermal brine through the heat exchangers and spinning the turbines.”
- Attribution
- Company reported
- Publisher
- Fervo Energy (SEC filing, Form 8-K exhibit)
- Dated
- 12 August 2026
- First public disclosure
- 12 August 2026
- State before
- Not established in reviewed sources
- Source read
- 11 November 2026
Inspect primary source: Fervo Energy (SEC filing, Form 8-K exhibit) ↗
What this does and does not establish
An exact passage match shows the source says this. It does not prove the underlying claim is true.