Project: stated targetCompany-reported
What was reported
a wholly owned subsidiary of Dow, filed a Construction Permit Application (“CPA”) with the NRC in March 2025 which was docketed in May 2025 for an 18-month review period with an expected review completion by late 2026 and receipt of the CPA expected in the first quarter of 2027.Regulator, government, developer and customer statements named in the Project Ledger · X-energy (SEC Form 10-Q, Q2 2026) statement · Aug 13, 2026 · Open the source ↗
What the evidence supports
That X-energy (SEC Form 10-Q, Q2 2026), the project's developer, published the quoted statement. It records a target, not something that has happened. Targets can move; earlier and later targets are both kept.
What remains unknown
Whether the target will be met. Any permission beyond the action quoted. A construction authorisation is not an operating licence, and one authority's action is not another's.
Source passages
Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.
X-energy (SEC Form 10-Q, Q2 2026) statementa wholly owned subsidiary of Dow, filed a Construction Permit Application (“CPA”) with the NRC in March 2025 which was docketed in May 2025 for an 18-month review period with an expected review completion by late 2026 and receipt of the CPA expected in the first quarter of 2027.Regulator, government, developer and customer statements named in the Project Ledger · X-energy (SEC Form 10-Q, Q2 2026) statement · Aug 13, 2026 · Open the source ↗
Revision history
- Revision 1 · Nov 11, 2026, 21:12 UTC
Long Mott Generating Station: permission issued targeted for Q1 2027