What was reported
As of June 30, 2026, we have been reimbursed approximately $546.7 million in funding under the ARDP.Regulator, government, developer and customer statements named in the Project Ledger · X-energy (SEC Form 10-Q, Q2 2026) statement · Aug 13, 2026 · Open the source ↗
What the evidence supports
That X-energy (SEC Form 10-Q, Q2 2026), the project's developer, published the quoted statement. It records "drawn / disbursed" for Cumulative ARDP reimbursements to X-energy as of June 30, 2026 (whole award: plant and TX-1 fuel facility work) under financing only. The amount is recorded as stated (About USD 546.7m).
What remains unknown
Drawn money does not prove the project is fully funded. Whether the project is fully financed, and whether conditional money has closed or been drawn, unless the quoted passage says so.
Source passages
Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.
X-energy (SEC Form 10-Q, Q2 2026) statementAs of June 30, 2026, we have been reimbursed approximately $546.7 million in funding under the ARDP.Regulator, government, developer and customer statements named in the Project Ledger · X-energy (SEC Form 10-Q, Q2 2026) statement · Aug 13, 2026 · Open the source ↗
Revision history
- Revision 1 · Nov 11, 2026, 21:13 UTC
Long Mott Generating Station: Cumulative ARDP reimbursements to X-energy as of June 30, 2026 (whole award: plant and TX-1 fuel facility work) (drawn / disbursed)
Spotted an error? Tell us. Corrections are published, never silent: see all corrections.