Project: financingCompany-reported
What was reported
While we have been notified that we were selected to receive an additional amount under the ARDP, any increase in the amount allocated to X-energy remains subject to execution of a subsequent contract award modification to the ARDP Agreement by the DOE’s contracting officer and continuation application approvals.Regulator, government, developer and customer statements named in the Project Ledger · X-energy (SEC Form 10-Q, Q2 2026) statement · Aug 13, 2026 · Open the source ↗
What the evidence supports
That X-energy (SEC Form 10-Q, Q2 2026), the project's developer, published the quoted statement. It records "conditional" for Additional ARDP allocation to X-energy: selected, but subject to a contract modification and continuation approvals (amount not stated) under financing only.
What remains unknown
Conditional is not final. Whether the project is fully financed, and whether conditional money has closed or been drawn, unless the quoted passage says so.
Source passages
Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.
X-energy (SEC Form 10-Q, Q2 2026) statementWhile we have been notified that we were selected to receive an additional amount under the ARDP, any increase in the amount allocated to X-energy remains subject to execution of a subsequent contract award modification to the ARDP Agreement by the DOE’s contracting officer and continuation application approvals.Regulator, government, developer and customer statements named in the Project Ledger · X-energy (SEC Form 10-Q, Q2 2026) statement · Aug 13, 2026 · Open the source ↗
Revision history
- Revision 1 · Nov 11, 2026, 21:13 UTC
Long Mott Generating Station: Additional ARDP allocation to X-energy: selected, but subject to a contract modification and continuation approvals (amount not stated) (conditional)