State

Permission issued

One permission is not every permission the project needs.

Open question

Which exact regulatory actions are on record, by which authority, for what scope?

  • Not established in reviewed sources: Operating licence (application expected in 2028, not yet filed)
  1. TargetTarget: application submitted, 2028Stated Date stated not shown on the source · Company reported · TerraPower (FAQ)

    Source: TerraPower (FAQ) ↗

  2. TargetTarget: permission issued, December 2026Stated 14 January 2025 · Company reported · TerraPower

    Source: TerraPower ↗

  3. Current statePermission issued16 March 2026 · Regulator issued · U.S. Nuclear Regulatory Commission (Federal Register)

    Before: Not established in reviewed sources. Source: U.S. Nuclear Regulatory Commission (Federal Register) ↗

  4. TargetTarget: permission issued, 2026Stated 18 June 2025 · Company reported · TerraPower

    Source: TerraPower ↗

  5. Earlier statementPermission issued8 May 2025 · Company reported · TerraPower

    Before: Not established in reviewed sources. Source: TerraPower ↗

  6. Earlier statementPermission issued14 January 2025 · Company reported · TerraPower

    Before: Not established in reviewed sources. Source: TerraPower ↗

  7. Earlier statementApplication accepted for review4 June 2024 · Regulator issued · U.S. Nuclear Regulatory Commission (Federal Register)

    Before: Not established in reviewed sources. Source: U.S. Nuclear Regulatory Commission (Federal Register) ↗

  8. Earlier statementApplication submitted14 May 2024 · Regulator issued · U.S. Nuclear Regulatory Commission (Federal Register)

    Before: Not established in reviewed sources. Source: U.S. Nuclear Regulatory Commission (Federal Register) ↗

Evidence detail

Permission issued

Construction Permit No. CPAR-1, Kemmerer Power Station Unit 1, immediately effective (not an operating licence)

One permission is not every permission the project needs.

“The U.S. Nuclear Regulatory Commission (NRC or the Commission) is providing notice of the issuance of Construction Permit (CP) No. CPAR-1 to US SFR Owner, LLC (USO) for the Kemmerer Power Station Unit 1 reactor facility and the associated record of decision (ROD).”
Attribution
Regulator issued
Publisher
U.S. Nuclear Regulatory Commission (Federal Register)
Dated
16 March 2026
First public disclosure
16 March 2026
State before
Not established in reviewed sources
Authority
U.S. Nuclear Regulatory Commission
Jurisdiction
United States (federal)
Source read
11 November 2026

Inspect primary source: U.S. Nuclear Regulatory Commission (Federal Register) ↗

What this does and does not establish

An exact passage match shows the source says this. It does not prove the underlying claim is true.

Watch permissionsInspect project history