Evidence detail
Permission issued
DOE Idaho Operations Office approval of the Preliminary Documented Safety Analysis under the Reactor Pilot Program (not authorization to operate)
One permission is not every permission the project needs.
“today announced that the U.S. Department of Energy’s (DOE’s) Idaho Operations Office has approved the Preliminary Documented Safety Analysis (PDSA) for Oklo’s Aurora powerhouse at Idaho National Laboratory (INL) under DOE’s Reactor Pilot Program (RPP).”
- Attribution
- Company reported
- Publisher
- Oklo
- Dated
- 11 June 2026
- First public disclosure
- 11 June 2026
- State before
- Not established in reviewed sources
- Authority
- U.S. Department of Energy, Idaho Operations Office
- Jurisdiction
- United States (federal)
- Source read
- 11 November 2026
Inspect primary source: Oklo ↗
What this does and does not establish
An exact passage match shows the source says this. It does not prove the underlying claim is true.