Evidence detail
Application submitted
Nuclear Safety Design Agreement and Preliminary Documented Safety Analysis submitted to DOE (first two of five DOE steps)
Submitted is not accepted for review, and neither is approval.
“we have also submitted the Nuclear Safety Design Agreement and the Preliminary Documented Safety Analysis to the DOE for the Aurora powerhouse at INL ("Aurora-INL"), which represent the first two of five steps in the DOE regulatory pathway for nuclear facility operation.”
- Attribution
- Company reported
- Publisher
- Oklo (SEC Form 10-K, 2025)
- Dated
- 17 March 2026
- First public disclosure
- 17 March 2026
- State before
- Not established in reviewed sources
- Authority
- U.S. Department of Energy
- Jurisdiction
- United States (federal)
- Source read
- 11 November 2026
Inspect primary source: Oklo (SEC Form 10-K, 2025) ↗
What this does and does not establish
An exact passage match shows the source says this. It does not prove the underlying claim is true.