Evidence detail
Application accepted for review
Selected under DOE's Reactor Pilot Program to proceed on the DOE authorization pathway (a selection, not an authorization)
Accepted for review is not approval.
“on August 13, 2025, Oklo and Atomic Alchemy were selected by the DOE for three of the eleven projects awarded under the newly established RPP. Oklo was selected for two projects, and Atomic Alchemy for one project. Among these, the Aurora–INL powerhouse was approved to proceed under DOE purview”
- Attribution
- Company reported
- Publisher
- Oklo (SEC Form 10-Q, Q3 2025)
- Dated
- 12 November 2025
- First public disclosure
- 12 November 2025
- State before
- Not established in reviewed sources
- Authority
- U.S. Department of Energy
- Jurisdiction
- United States (federal)
- Source read
- 11 November 2026
Inspect primary source: Oklo (SEC Form 10-Q, Q3 2025) ↗
What this does and does not establish
An exact passage match shows the source says this. It does not prove the underlying claim is true.