Evidence detail
Permission issued
DOE site use permit at INL for the Aurora powerhouse (a site permit, not a construction or operating authorization)
One permission is not every permission the project needs.
“Aurora-INL will be the first of Oklo’s planned fast fission power plants and has been granted access to recovered fuel from the Experimental Breeder Reactor-II (EBR-II) following a competitive DOE process launched in 2019, the same year Oklo received a site-use permit at INL for the Aurora powerhouse.”
- Attribution
- Company reported
- Publisher
- Oklo
- Dated
- 11 June 2026
- First public disclosure
- 11 June 2026
- State before
- Not established in reviewed sources
- Authority
- U.S. Department of Energy
- Jurisdiction
- United States (federal)
- Source read
- 11 November 2026
Inspect primary source: Oklo ↗
What this does and does not establish
An exact passage match shows the source says this. It does not prove the underlying claim is true.