Project: stated targetCompany-published
What was reported
The company began non-nuclear construction activities on the site of the first plant last year and expects regulatory approval for the nuclear reactor next year.Regulator, government, developer and customer statements named in the Project Ledger · TerraPower statement · Jun 18, 2025 · Open the source ↗
What the evidence supports
That TerraPower, the project's developer, published the quoted statement. It records a target, not something that has happened. Targets can move; earlier and later targets are both kept.
What remains unknown
Whether the target will be met. Any permission beyond the action quoted. A construction authorisation is not an operating licence, and one authority's action is not another's.
Source passages
Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.
TerraPower statementThe company began non-nuclear construction activities on the site of the first plant last year and expects regulatory approval for the nuclear reactor next year.Regulator, government, developer and customer statements named in the Project Ledger · TerraPower statement · Jun 18, 2025 · Open the source ↗
Revision history
- Revision 1 · Nov 11, 2026, 21:12 UTC
Natrium Kemmerer Unit 1: permission issued targeted for 2026
Spotted an error? Tell us. Corrections are published, never silent: see all corrections.