Project: constructionCompany-published

What was reported

Helion continues to build Orion in Malaga, with the assembly and office building construction complete. Now, the company can proceed with work on the generator building, for which initial earthwork began in the spring of 2026.Regulator, government, developer and customer statements named in the Project Ledger · Helion Energy statement · Jun 16, 2026 · Open the source ↗

What the evidence supports

That Helion Energy, the project's developer, published the quoted statement. It records "construction" for Assembly and office building construction complete; initial earthwork for the generator building began spring 2026 under construction only.

What remains unknown

Construction is not commissioning. Progress in any other dimension or unit. Physical work does not establish permissions, financing, customers or commissioning.

Source passages

Exact excerpts from the source, with links. Quotes are checked character for character against our stored copy.

Helion Energy statementHelion continues to build Orion in Malaga, with the assembly and office building construction complete. Now, the company can proceed with work on the generator building, for which initial earthwork began in the spring of 2026.Regulator, government, developer and customer statements named in the Project Ledger · Helion Energy statement · Jun 16, 2026 · Open the source ↗

Revision history

  1. Revision 1 · Nov 11, 2026, 21:14 UTC

    Orion: Assembly and office building construction complete; initial earthwork for the generator building began spring 2026 (construction)